$15.4 million construction of a new data center for Oregon Health and Science University, with 3.8 MW of storage space providing five times the amount of current capacity. Initial infrastructure includes two primary transformers with room to add a third at a later date, along with three primary switches, and three planned UPS systems. Structurally, a geodesic dome was constructed to house and protect the data center providing a greener partial passive cooling approach with minimal mechanical equipment.
Facts
Service: Construction
Mark segment: Telecommunications
Start date: 2013
Completion date: 2014
Clients: Oregon Health & Science University
Country: United States
City: Beaverton
Project status: Completed